Route 242 between Route 54 and the Miller County line – Roadway resurfacing and shoulder widening is underway. One lane will be open and crews will flag traffic through the work area.

The following is a listing of general highway maintenance and construction work in the mid-Missouri area for the two-week period of May 13-24, 2019. Weather conditions may postpone the work schedule. Many projects will include lane closures that could cause traffic delays.

MoDOT reminds motorists to buckle up, slow down, follow posted signs and drive safely through work areas. For more information about a project, please contact MoDOT at 1-888-ASK-MoDOT (275-6636) or visit www.modot.org/modot-central-district. You can also follow MoDOT’s Central Missouri District on Twitter and Facebook at https://twitter.com/MoDOT_Central and MoDOT Central Missouri District.                                          

All Counties

Daylight Hours

Mowing, striping, brush cutting and guardrail repair continues in various locations.  Motorists should travel with care and be alert to slow-moving equipment along the road.

Camden County

Daylight/Overnight Hours

Route 242 between Route 54 and the Miller County line – Roadway resurfacing and shoulder widening is underway.  One lane will be open and crews will flag traffic through the work area.

Route MM between Route 242 and Route TT – Roadway resurfacing and shoulder widening is underway. One lane will be open and crews will flag traffic through the work area.

Route KK between Osage Beach Parkway and Turkey Bend Road – Roadway resurfacing and shoulder widening is underway. One lane will be open and crews will flag traffic through the work area.

Business Route 54 between Route 242 and Route MM – Roadway resurfacing and shoulder widening is underway.  One lane will be open and crews will flag traffic through the work area.

Overnight Hours

Route 5 between Route 7 and Route 64 in Laclede County – Pavement repair continues. One lane will be open and crews will flag traffic through the work area. The project is scheduled for completion in May.

Daylight Hours

Route 54 between Route KK and East Valley Drive – Pavement improvement and J-Turn installation continues. The project is scheduled for completion in August.

Route J over the Little Niangua River north of Deer Meadow Road - New bridge construction continues. Much of the work will take place off the roadway. Minimal traffic interruptions are expected through the work area.

Miller County 

Daylight/Overnight Hours

Route 54 over Business Route 54 in Eldon – Bridge rehabilitation in the eastbound and westbound lanes continues. One eastbound lane and one westbound lane will be open through the work area. The project is scheduled for completion in mid-May.

Route 54 over Old Tuscumbia Road, east of Route 52 – Bridge rehabilitation in the eastbound and westbound lanes continues. One eastbound lane and one westbound lane will be open through the work area. The project is scheduled for completion in mid-May.

Morgan County

Daylight Hours

Route 5 between Route 52 and Zulaue Street – Roadside maintenance will take place Monday, May 13 through Thursday, May 16. One lane will be open and crews will flag traffic through the work area.

Route 52 between Route 5 and Westview Drive – Roadside maintenance will take place Monday, May 13 and Tuesday, May 14. One lane will be open and crews will flag traffic through the work area.

Route C between Route 52 and Route 54 in Cole County – Guardrail installation, milling and resurfacing continues. 

Milling work will take place between Jefferson City and Russellville the week of May 13.  One lane will be open and crews will flag traffic through the work area.