  • The following is a listing of general highway maintenance and construction work in the mid-Missouri area for the two-week period of September 30 - October 11, 2013. Weather conditions may cause postponements in the work schedule. Other construction or maintenance work may occur on other roadways throughout the area. Many projects will include lane closures, and delays can be expected.
    • email print
      Comment
  • The following is a listing of general highway maintenance and construction work in the mid-Missouri area for the two-week period of September 30 - October 11, 2013. Weather conditions may cause postponements in the work schedule. Other construction or maintenance work may occur on other roadways throughout the area. Many projects will include lane closures, and delays can be expected.
    Camden County
    Daylight/Overnight Hours
    * Route 5 bridge over the Lake of the Ozarks at Hurricane Deck - Bridge replacement is nearing completion. The new bridge is open to traffic. The contractor will perform general cleanup under the bridge and prepare to start demolishing the old Hurricane Deck Bridge over the next several months. The work will have little impact on traffic.
    Daylight Hours
    * Route 7 between Route J and Route DD - Culvert pipe maintenance will take place Monday, September 30 through Thursday, October 3. One lane will be open, and crews will flag traffic through the work area.
    * Route 54 between Old Route 5 and the Niangua Bridge - Roadway resurfacing, widening of shoulders and installation of rumble strips continues. Rumble strips will be installed on centerline and edgelines between Business Route 5 and the Niangua Bridge during the week of September 30. This will be a moving operation. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in the fall.
    * Route J over the Little Niangua River - Bridge maintenance will take place Monday, September 30 through Thursday, October 17. Periodic lane closures and full closures of the bridge are likely as the work takes place. Motorists are advised to seek an alternate route around the work area.
    Miller County
    Daylight Hours
    * Route 17 between Route 42 and Business Loop 44 in Pulaski County - Roadway resurfacing and widening of shoulders continues. One lane is open, and crews will flag traffic through the work area. The project is scheduled for completion in the fall.
    * Route D between Columbia Avenue and the end of state maintenance - Roadway maintenance will take place Tuesday, October 8 through Thursday, October 10. One lane will be open, and crews will flag traffic through the work area.
    * Route U between Route 42 and Route EE - Roadway maintenance will take place on Monday, October 7. One lane will be open, and crews will flag traffic through the work area.
    * Route AA between Route 54 and Route C in Cole County - Roadway maintenance will take place Wednesday, October 2 and Thursday, October 3. One lane will be open, and crews will flag traffic through the work area.
    * Route BB between Route 42 and Route 133 in Maries County - Roadway maintenance will take place Monday, September 30 through Thursday, October 3. One lane will be open, and crews will flag traffic through the work area.
    Page 2 of 2 - Morgan County
    Daylight Hours
    * Route 5 between Route 52 and the Niangua Bridge in Camden County - Roadway resurfacing, widening of shoulders, and installation of rumble strips is under way. The contractor has started building the new four-foot shoulders between Route 135 and Route TT.  Rumble strips will be installed on the centerline and edgelines from Versailles to Route J during the week of September 30. This will be a moving operation. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in the fall.