  • The following is a listing of general highway maintenance and construction work in the mid-Missouri area for the two-week period of April 1-12, 2013.
    • email print
  • The following is a listing of general highway maintenance and construction work in the mid-Missouri area for the two-week period of April 1-12, 2013. Weather conditions may cause postponements in the work schedule. Other construction or maintenance work may occur on other roadways throughout the area. Many projects will include lane closures, and delays can be expected.
    Camden County
    Daylight/Overnight Hours
    * Route 5 bridge over the Lake of the Ozarks at Hurricane Deck – Bridge replacement continues.  Much of the work currently taking place will not affect traffic. The entire project is scheduled for completion in spring 2014.
    Daylight Hours
    * Route TT between Route F and the end of state maintenance – Roadside maintenance will take place Monday, April 1 through Thursday, April 11. One lane will be open, and crews will flag traffic through the work area.
    Miller County
    Daylight/Overnight Hours
    * Route 54 bridge over the Osage River east of Wood River Road – Bridge rehabilitation in the westbound lanes is under way. One lane will be open through the work area. The entire project is scheduled for completion in May.
    Daylight Hours
    * Route 42 between Route 17 and Route 134 – Shoulder widening work will resume on Monday, April 1. One lane will be open, and a pilot car will guide traffic through the work area. The entire project is scheduled for completion in July.
    * Route 42 between Route 17 and Route TT – Roadside maintenance will take place Wednesday, April 3 through Thursday, April 4.  One lane will be open, and crews will flag traffic through the work area.
    * Route 52 between Route 17 and Route PP – Roadside maintenance will take place Monday, April 1 through Thursday, April 11. One lane will be open, and crews will flag traffic through the work area.
    * Route 52 between Route 17 and Woods Road – Culvert pipe replacement will take place Monday, April 1 through Friday, April 12. One lane will be open, and crews will flag traffic through the work area.
    * Route K between Bethany Road and Cannor Ridge Road – Roadside maintenance will take place on Tuesday, April 2. One lane will be open, and crews will flag traffic through the work area.
    * Route Y between Route 52 and Hackler Road – Culvert pipe replacement will take place Monday, April 1 through Friday, April 12. One lane will be open, and crews will flag traffic through the work area.
    * Route BB between Route 42 and Route 133 – Roadside maintenance will take place Monday, April 1 through Thursday, April 4. One lane will be open, and crews will flag traffic through the work area.