The Lake News Online
  • Weekly road outlook

  • The following is a listing of general highway maintenance and construction work in the mid-Missouri area for the two-week period of March 18 – March 29, 2013. Weather conditions may cause postponements in the work schedule. Other construction or maintenance work may occur on other roadways throughout the area. Many projects will include lane closures, and delays can be expected.
    • email print
      Comment
  • The following is a listing of general highway maintenance and construction work in the mid-Missouri area for the two-week period of March 18 – March 29, 2013.  Weather conditions may cause postponements in the work schedule. Other construction or maintenance work may occur on other roadways throughout the area. Many projects will include lane closures, and delays can be expected.
    Camden County
    Daylight/Overnight Hours
    *Route 5 bridge over the Lake of the Ozarks at Hurricane Deck – Bridge replacement continues. Crews continue to set steel girders on the concrete piers. This will require a closure of the existing Hurricane Deck Bridge several times a day for 15 minutes at a time. This process continues over the next 3 to 4 months.  The entire project is scheduled for completion in spring 2014.
    Daylight Hours
    *Route 7 between Route 5 and Route E – Roadside maintenance will take place Monday, March 18 through Thursday, March 21. One lane will be open, and crews will flag traffic through the work area.
    *Route TT between Route F and Route MM – Roadside maintenance will take place Monday, March 18 through Thursday, March 21. One lane will be open, and crews will flag traffic through the work area.
    Miller County
    Daylight/Overnight Hours
    *Route 54 bridge over the Osage River east of Wood River Road – Bridge rehabilitation in the westbound lanes is under way. One lane will be open through the work area. The entire project is scheduled for completion in May.
    Daylight Hours
    *Route 42 between Route 17 and Route 134 – Shoulder widening work will resume in April. The entire project is scheduled for completion in July 2013.
    *Route 42 between Route 17 and Route TT – Roadside maintenance will take place Thursday March 21 and Tuesday, March 26.  One lane will be open, and crews will flag traffic through the work area.
    *Route 52 between Route 17 and Woods Road – Culvert pipe replacement will take place Monday, March 18 through Thursday, March 28.  One lane will be open, and crews will flag traffic through the work area.
    *Route 87 between Route P and Boulder Road – Roadside maintenance will take place Monday, March 18 through Thursday, March 28. One lane will be open, and crews will flag traffic through the work area.
    *Route D between Route 54 and the end of state maintenance – Roadside maintenance will take place Wednesday, March 27 and Thursday, March 28. One lane will be open, and crews will flag traffic through the work area.
    *Route K between Bethany Road and Cannor Ridge Road – Roadside maintenance will take place Monday, March 18 and Tuesday, March 19. One lane will be open, and crews will flag traffic through the work area.
    *Route Y between Route 52 and Hackler Road – Culvert pipe replacement will take place Monday, March 18 through Thursday, March 21. One lane will be open, and crews will flag traffic through the work area.
    Page 2 of 2 - Morgan County
    Daylight Hours
    *Route T south of Briar Patch Road – Culvert pipe replacement will take place Monday, March 18 and Tuesday, March 19. One lane will be open, and crews will flag traffic through the work area.

        calendar