The Lake News Online
  • Weekly road outlook

  • The following is a listing of general highway maintenance and construction work in the mid-Missouri area for the two-week period of January 7 – 18, 2013. Weather conditions may cause postponements in the work schedule. Other construction or maintenance work may occur on other roadways throughout the area. Many projects will include lane closures, and delays can be expected.
    • email print
      Comment
  • The following is a listing of general highway maintenance and construction work in the mid-Missouri area for the two-week period of January 7 – 18, 2013.  Weather conditions may cause postponements in the work schedule. Other construction or maintenance work may occur on other roadways throughout the area. Many projects will include lane closures, and delays can be expected.
     
    Camden County
    Daylight/Overnight Hours
    * Route 5 bridge over the Lake of the Ozarks at Hurricane Deck – Bridge replacement continues.  Crews continue to set steel girders on the concrete piers. This will require a closure of the existing Hurricane Deck Bridge several times a day for 15 minutes at a time. This process will take place over the next 3 to 4 months.
    The entire project is scheduled for completion in spring 2014.
    Daylight Hours
    * Route 7 between Route 5 and Route T – Roadside maintenance will take place Monday, January 7 through Friday, January 11.  One lane will be open, and crews will flag traffic through the work area.
    Miller County
    Daylight Hours
    * Route 42 between Route 17 and Route 134 – Shoulder widening work will resume in the spring.   The entire project is scheduled for completion in July 2013.
    * Route 52 bridge over Route 54 – Bridge maintenance will take place Monday, January 7 through Friday, January 11.  One lane will be open, and crews will flag traffic through the work area.
    * Route 54 between Route 242 and Route FF – Bridge maintenance in various locations will take place Monday, January 7 through Friday, January 11.  One lane will be open, and crews will flag traffic through the work area.
    * Route 87 at Gerhart Street in Eldon – Culvert pipe replacement will take place Monday, January 14 through Friday, January 18.  One lane will be open, and crews will flag traffic through the work area.
    * Route 87 between Greenridge Road and Boulder Road – Roadside maintenance will take place Monday, January 14 through Friday, January 18.  One lane will be open, and crews will flag traffic through the work area.
    * Route A between Route 17 and Route 42 – Culvert pipe replacement and roadside maintenance will take place Monday, January 7 through Friday, January 18.  One lane will be open, and crews will flag traffic through the work area.
    * Route Z between Blue Springs Drive and Dusky Drive – Roadside maintenance will take place Monday, January 14 through Friday, January 18.  One lane will be open, and crews will flag traffic through the work area.

        calendar